About Us | Gallery Search | About this Site | About Heavy Construction 

The Builders

Men and Women Doing the Work
Job Glossary
People Behind the Work
In Their Own Words
Construction Close-up
The Companies Behind the Work
Skyway: KFM
Geofill: Gordon N. Ball, Inc.
Design: T.Y. Lin International / Moffatt & Nichol
Subcontractors
The Unions
Operating Engineers
Northern California District Council of Laborers
Piledrivers
Carpenters
Ironworkers
Cement Masons
Masters, Mates & Pilots
The Teamsters
The Government Partners
Caltrans
Other Agencies

Construction Close-up: On-Site Batch Plant Churns Out Volumes of Concrete

The roar of heavy machinery nearly upstages the whoosh of traffic on a narrow, man-made finger of land pointing from the Oakland shoreline near the East Span construction site.

More brawny than graceful, a complex of conveyer belts, tanks and massive cylinders churns noisily. Hillocks of sand and gravel disappear into the maw, to reemerge as grey form-fitting slurry needed to construct an engineering marvel

Strength, versatility and timing are equal parts of the mix at the batch plant—a specially built on-site factory supplying the basic raw material for the bridge—super strong concrete.

To withstand the full fury of a major seismic event, the concrete must be perfect. To ensure that the finished concrete will be uniformly strong, the composition is continuously monitored and adjusted. As the temperature and humidity change so do the ingredients, with water, sand, chemical binders and cement all variables.

Though tiny compared to the bridge's monumental scale, a combination of just-in-time delivery and immediate distribution, mean the plant produces far more than seems possible from an initial glance.

The Batch Plant is owned and operated by California Readymix, Inc., a nine-employee subsidiary of RMC Pacific Materials. RMC Pacific Materials is a division of RMC Group Plc, one of the largest makers of ready mixed in the world. The London-based firm has nearly 32,000 employees and operations in 25 nations.

Tandem tractor-trailers deliver 20 loads of gravel and sand to the site daily, in a relay race of just-in-time production. After a carefully monitored mixing process, the concrete is pumped through a sluice-like system of conveyor belts and onto one of three custom built barges that began life as a sketch on the back of an envelope. The barges, Kathy, Margo and Micki, named in honor of the wives of three executives, deliver the goods.

Once mixed, a chemical reaction begins in the concrete, generating heat as it begins hardening, much like papier-mâché. To slow that process—assuring the concrete is poured at the optimum consistency—ice, and water, is folded into the mixture.

Keeping it cool is key. Engineers set up an ice-making machine, akin to a super-sized hotel hallway ice-maker to help with this. Ensconced essentially in the back of an 18-wheeler, the ice plant is capable of producing up to 100 tons of ice a day. Once aboard a barge for the roughly 30-minute journey to the work site, the concrete is further cooled with liquid nitrogen.

The concrete mixers and other machinery operate with vegetable oil in place of hydraulic fluid, sharply reducing potential environmental damage in the event of spillage.

The plant produces between 6,500 and 8,000 cubic yards of concrete per month. A cubic yard is an area three feet long by three feet wide by three feet deep—about the volume of a standard washing machine.

The largest single pour of material coming out of the batch plant is 706 cubic yards for a pair of pilings. Under the existing contract the batch plant will produce 183,120 cubic yards of concrete—just for the "Skyway" segment alone. That's enough concrete to build an inch deep, four-foot wide sidewalk 2,809 miles, practically the distance between San Francisco and the East Coast.

The batch plant production figures excludes what will be needed for the cable-stayed suspension portion of the bridge. A contract for that section hasn't been awarded, so the concrete for that part of the span may be produced elsewhere.

Another 145,000 cubic yards of concrete for the actual roadway is being produced seperately at the Stockton "Pre-cast Yard."

HOW IT'S DONE:

The raw materials are carefully mixed in a gigantic enclosed mixing bowl—similar to the rotating tank on a cement mixer truck. Two large cylindrical containers, one filled with portland cement, the other with fly ash and slag (a steel production byproduct), stand above the central mixer, connected by a network of pipes. Water is fed in through ducts. Ice, rock and sand arrive via conveyor belts.

Maintaining the mixture to the exact specifications is vital. Slight shifts in temperature and humidity require constant tweaking of the mix. From a control board in a trailer, Harold Arnaudon, Batch Plant / Ice Plant Operator, keeps a watchful eye on video monitors, pressing buttons to add chemicals, managing the chemical reaction, giving workers at the pouring site the proper amount of time to pour before the concrete hardens.

The massive mixing bowl homogenizes the final product, feeding conveyors once a barge moves into position. Barges ferry the wet concrete to the job site, docking with a pier. Massive pumps spring to life, driving the entire load through a pipe and into place in less than 20 minutes. All the while rising and falling waves make the barge and the pipe bob up and down, echoing the Bay itself.

As the concrete advances lava-like into a pour, the curing process is already under way. It will take just three hours for the fresh concrete to support a man's weight and 14 days to design strength.

Caltrans inspectors and quality control technicians from California Ready Mix and KFM monitor the composition of the mix and the entire process of the pour, assuring that the future Bay Bridge now taking shape will stand tall in the next earthquake and serve Northern California well into the 22nd century.

November, 2003.


Construction Close-Up / Archives
Building the Cofferdams—Holes in the Bay November, 2002
Boxes, Bases and Towers—Foundation Work Picks Up February, 2003
Nine Miles of Pipe: Piledriving Now Underway March, 2003
The Skyway Pile Head Welding—Turning Up the Heat in Close Quarters August, 2003
On-Site Batch Plant Churns Out Volumes of Concrete November 2003
Cranes Dominating the Bay Skyline are East Span Project's Heavy Lifters February 2005



The Bridge | The Builders | The Projects | Photo Galleries | History | Build Your Bridge
About Us | Gallery Search | About this Site | About Heavy Construction | Contact Us