Oakland -- In the year since Gov. Gray Davis 
              donned a Caltrans hard hat and declared construction of the new 
              eastern span of the Bay Bridge under way, it's been difficult for 
              anyone but the most curious of commuters to spot much progress. 
               
            That is about to change. The work will soon come into 
              full view -- and earshot.  
            "People will start to notice," said Jeff 
              Weiss, a Caltrans spokesman. "They will definitely see it now." 
             
            Most of the early work on the $2.6 billion bridge 
              involved logistics -- hiring crews, setting up construction headquarters, 
              dredging and bulldozing. Now it's time for the heavy-duty construction, 
              and crews toiling aboard enormous barges beneath the existing bridge, 
              often in wind and rain, have started the lengthy task of building 
              the foundation for the new span.  
            Sometime early this month, workers will begin the 
              noisy task of pounding tubular piles as long as a football field 
              through the muck and sand of the bay floor and into the more solid 
              Alameda alluvia -- a firm mixture of clay and gravel so hard, says 
              Caltrans bridge engineer Mark Woods, that most people would consider 
              it rock.  
            The huge pneumatic hammers used to pound the 7 1/2-foot-diameter 
              piles will loom just north of the bridge, about 100 feet higher 
              than the traffic decks. If motorists somehow don't notice the towering 
              equipment, they'll probably hear the noise. A relentless "clong-clong-clong-clong-clong" 
              will reverberate for the two years it takes to pound the piles. 
             
            In all, 160 piles will be slammed at a slight angle 
              into the bay floor. They will anchor the 28 columns that will hold 
              up the 1 1/2-mile-long twin concrete viaducts of the "skyway" 
              portion span. The viaducts will reach from the mudflats in Oakland 
              to the new bridge's signature single-tower suspension span, which 
              will stretch to Yerba Buena Island.  
            But before the bridge can begin to rise from the water, 
              workers have to build the foundation -- a multipart process that 
              starts by building the boxes formally known as cofferdams.  
            The cofferdam construction has been under way since 
              fall, when a waterborne crew started pounding 85-foot interlocking 
              steel sheets about 30 feet deep into the mud, outlining the site 
              of each future pier.  
            The 100 or so workers building the cofferdams work 
              in unusual conditions. They're hauled by boat to huge barges in 
              the bay, and they labor amid passing vessels and wildlife, the roar 
              of traffic on the bridge and the winter storms. Rain doesn't delay 
              construction, Woods said, but gusting winds can be hazardous and 
              force a break in the work.  
            "We're stopped more by wind than by the high 
              seas," he said, noting that since the workers are already working 
              on, and in, the water, they aren't worried about getting wet.  
            Once the cofferdam walls are in place, crane operators 
              scoop out the mud from the outlined area and dump in a 6-foot layer 
              of rock and gravel. Then a 900-ton steel "footing box" 
              -- with holes where the piles will be driven through -- is placed 
              atop the gravel.  
            After that step is done, more gravel is added between 
              the footing box and the cofferdam walls, and huge sump pumps are 
              installed to "de-water" the dam --  
            in other words, pump it dry.  
             
              GUIDANCE SYSTEM 
            The last piece to put in place inside the cofferdam 
              before the piles can be driven is a 150-foot-tall template. The 
              giant guide sits on top of the footing box and holds the piles in 
              place while they're pounded.  
            Finally, using some of the world's largest pile-driving 
              hammers, crews pound the tubular steel pilings through the slots 
              of the footing box and into the bay floor. The piles are so long 
              they arrive on barges in two sections -- one about 220 feet long, 
              the other 110 feet. The longest segment will be pushed into the 
              bay first, then crews will weld on the second length, and the pounding 
              will resume.  
            Once the piles for each pier are pounded -- most will 
              have six -- workers weld the connection where the piles meet the 
              footing box, slip rebar into the piles and pour concrete into both 
              the piles and the footing box. At that point,  
            the foundation will be ready to support a column rising 
              from the bay.  
            Each foundation, said Woods, takes about nine months 
              from start to finish.  
            "You can see why it costs so much to build a 
              bridge," Weiss said.  
            The $1.04 billion contract to build the skyway -- 
              awarded to the KFM consortium of Kiewit Pacific of Omaha, FCI Constructors 
              of San Jose and Manson Construction of Seattle -- is the largest 
              ever awarded by Caltrans.  
            Designers envisioned the eastern span as a thin white 
              line hovering above the bay, then bursting into a grand spire of 
              steel and cable just east of Yerba Buena Island.  
            A huge and complex project, it is actually two bridges 
              -- the side-by-side viaducts of the skyway and the single-tower 
              suspension span, which will join in the middle of the bay. Construction 
              also includes separate structures that link the new bridge to the 
              eastern shoreline and the tunnel at Yerba Buena. At times, crews 
              will be at work on different sections of the new span at the same 
              time.  
            The skyway, the longest stretch of the span, will 
              emerge from the bay gradually, east to west, a few pieces at a time, 
              and one viaduct at a time. The twin concrete viaducts will each 
              feature five lanes with emergency shoulders.  
            
               
             |